Over the last 3 months I’ve been busy working hard on coordinating the BIM for an existing infrastructure study of a hospital. The site consists of everything from heritage listed sandstone buildings constructed in the 1800s where for obvious reasons there are no existing drawings to a building that’s currently in the final stages of construction and has been fully designed and coordinated in BIM. The infrastructure study involved locating assets and services that interconnected between buildings within relatively accurate space within the BIM at LOD 200 as per the BIMForum guidelines.
When it came to the BIM, we decided to work with one building per MEP model which meant we had 28 MEP building models, 28 architecture building models that were created using a series of stacked DWG files and 4 site models. The obvious problem with so many models was going to be the consistency of the data and how we would go about verifying that data. Ensuring that we had all 60 models with the same…